+966 59 039 1000info@skylius.comSun–Thu 9:00–4:30 · Sat 12:00–5:00
Maintenance Contracts

From Pay Per Ticket to a full IT department

Flexible support plans with defined SLAs, sized to your business.

Pay Per TicketOn demand
SLA ContractDefined response
Full IT deptFully outsourced
Sized to your businessExplore plans
Contracting & Technical Works

Contracting & Technical Works

Construction, civil, electromechanical and electrical works delivered to handover.

At a glance
Covers
General constructionCivil worksElectrical worksElectromechanicalWater & sewage networksPump stationsSite preparation
Guides
Lump sum vs re-measured · Electrical: MDB, SMDB, DB · UPS vs generator · Hold points & inspections
How we work
Survey → Plan → Build → Inspect & test → Hand over
Trades clash on site

Ceilings close before the data cabling is in, and walls get opened twice. Our fix: One coordinated programme with hold points.

See the common problems
Nobody owns the interface

Civil blames MEP, MEP blames electrical, and you referee. Our fix: A single contractor accountable for the whole.

See the common problems
Power designed as an afterthought

No capacity for servers, UPS or EV chargers, and breakers trip. Our fix: Load surveys and electrical design up front.

See the common problems
Interactive · coordinated programme

Pick a project and its scopes, then drag through the weeks. You'll see which trades are on site and which hold points keep rework off your budget.

Try the coordinated programme
Request a consultation

Answer a few quick questions and a Skylius specialist will prepare practical recommendations.

Request a consultation

Five contractors, five schedules, and nobody owns the clashes.

We deliver civil, electrical, electromechanical and technical fit-out works under one programme, coordinated with the low-current and IT systems from day one, then tested and handed over with full documentation.

Man in orange and black vest wearing white helmet holding yellow and black power tool – Contracting & Technical Works
 Zero-rework handoverAs-builts + test sheets delivered
Week 9 hold point passedAbove-ceiling inspection signed

Sound familiar?

Where projects lose time and money.

Most overruns come from the gaps between trades, not from the work itself.

Trades clash on site

Ceilings close before the data cabling is in, and walls get opened twice.

We fix it: one coordinated programme with hold points.

Nobody owns the interface

Civil blames MEP, MEP blames electrical, and you referee.

We fix it: a single contractor accountable for the whole.

Power designed as an afterthought

No capacity for servers, UPS or EV chargers, and breakers trip.

We fix it: load surveys and electrical design up front.

No as-built drawings

At handover you get keys, not the documents you need to maintain the building.

We fix it: as-builts, test sheets and O&M manuals.

Late handover

Testing starts in the last week, and snags push opening day.

We fix it: commissioning planned from the start.

Utility connections delayed

Water, sewer or power connections hold up occupancy.

We fix it: early coordination of networks and connections.

Interactive · coordinated programme

One programme, every trade in sequence.

Pick a project and its scopes, then drag through the weeks. You'll see which trades are on site and which hold points keep rework off your budget.

Project type
Scopes included
Wk 1

On site this week

Hold point / coordination

Programme

0weeks (indicative)Discuss this project

Interactive · power & UPS sizing

How much backup power do your critical systems need?

Add your critical equipment and choose a runtime. You'll get the load, an indicative UPS rating and a generator range to start the conversation.

UPS runtime on battery
Generator backup?

Indicative power scope

0
Critical load
0
Recommended UPS rating
0
Battery energy needed
0
Generator range (with AC & lighting)
UPS loading at this rating0%

Indicative only. Uses typical power draw and a 0.9 power factor, with 25% headroom on the UPS. Final sizing follows a site load survey, cable sizing and discrimination study.

Send this load list on WhatsApp

Owner's guide

Contracting decisions, explained simply.

What to clarify before signing a works contract.

Lump sum vs re-measured

How you pay changes how risk is shared.

Lump sum

A fixed price for a defined scope. Clear budget, but changes cost extra.

Re-measured

Paid on actual quantities at agreed rates. Flexible, needs tight measurement.

Design & build

One party designs and builds. Fewer interfaces, but define performance clearly.

Ask for: a priced BOQ, a variation procedure and payment milestones tied to progress.

Electrical: MDB, SMDB, DB

Power flows through a hierarchy of boards, so size each for growth.

MDB

Main distribution board fed from the utility or transformer.

SMDB

Sub-main boards per floor, zone or plant area.

DB

Final boards feeding lighting, sockets and equipment, with spare ways.

Tip: keep 20–30% spare capacity for future IT, UPS and EV charging.

UPS vs generator

They complement each other. Most critical sites need both.

UPS

Instant, clean power for minutes to hours. Protects IT, security and controls.

Generator

Long-duration backup for the wider building, after a start-up delay.

Together

UPS bridges the gap until the generator takes the load. ATS switches automatically.

Don't forget: earthing, surge protection and battery replacement cycles.

Hold points & inspections

Checking at the right moment is cheaper than opening finished work.

Before cover-up

Above-ceiling, in-wall and in-slab services inspected and photographed.

Before energising

Insulation resistance, polarity and earthing tests on every circuit.

Before handover

Integrated systems tests, authority inspections and snagging.

Rule of thumb: no hold point sign-off, no next trade.

Water & sewage networks

Underground works need accurate surveys and testing before backfill.

Survey & design

Existing utilities located. Levels and gradients confirmed.

Construction

Pipe bedding, jointing, manholes and connections to approved details.

Testing

Pressure tests for water, leak and CCTV inspection for sewers before backfilling.

Note: connection approvals can take time. Start the process early.

Handover documents

What you should receive at the end of every project.

As-built drawings

The installed reality, not the tender design.

Test & commissioning sheets

Signed results for every system and circuit.

O&M + warranties

Manuals, spare parts lists, warranty certificates and training records.

Ask for it in the contract: the final payment linked to complete handover documents.

How we work

From site survey to handover, one accountable team.

A single programme for civil, MEP, electrical and technical systems.

01

Survey

Site survey, existing services, loads and authority requirements.

You getSurvey report + risks
02

Plan

Programme, BOQ, method statements and coordination drawings.

You getIntegrated programme
03

Build

Civil, electrical, MEP and fit-out works with daily site supervision.

You getWeekly progress reports
04

Inspect & test

Hold-point inspections, circuit testing and integrated commissioning.

You getSigned test sheets
05

Hand over

Snagging, as-built drawings, O&M manuals and training.

You getComplete handover file
Electrical distribution board with circuit breakers and wiring
Electrical & technical rooms
Architectural floor plan drawings on a desk
Handover & documentation
Completed commercial building delivered with coordinated systems
Delivered to handover

Technology we work with

Equipment and systems we install and integrate.

Brand-neutral. We select equipment to the project specification and approvals.View all brands →

FAQ

Questions clients ask us.

Have a different question? A specialist will reply on WhatsApp.

Ask on WhatsApp

Man in orange vest wearing yellow hard hat – Contracting & Technical Works

Yes. That's the point: civil, electrical, electromechanical and low-current works under one programme, so interfaces are coordinated, not argued over.

Yes. We build to the approved design and specifications, raise technical queries early, and propose value engineering only with your approval.

Yes. We do network construction and connections, and pump stations including the electrical, MCC and control works, tested before handover.

Weekly progress reports with photos, a look-ahead programme, open issues and hold-point status, plus site meetings at agreed intervals.

As-built drawings, test and commissioning sheets, O&M manuals, warranties, spare parts lists and training records.

Yes. We phase works, schedule noisy or shutdown activities out of hours, and agree safety and access rules with your facility team.

We work to an agreed programme, report progress weekly and flag risks early, so decisions are made before they cause delays.

Defects are handled under the defects liability terms in your contract. The handover pack lists contacts, and we attend to reported defects.

Site visit

One contractor, one programme, no gaps between trades.

Share your drawings or describe the site. We'll visit, review the scope and propose a coordinated plan and BOQ.

Request a site visit →WhatsApp +966 59 039 1000Khobar · serving the Eastern Province and across KSA
Give us a call

Available Sunday–Thursday 9:00 AM–4:30 PM, Saturday 12:00–5:00 PM. Friday closed.

Send us a message

Send your message anytime you want.

We use essential cookies to run this site. Cookie Policy